Practical Bently Nevada TSI Commissioning Checklist for New Rotating Machinery Projects
Unchecked TSI commissioning errors often trigger costly rotating machine trips. Field data shows that 42% of turbine startup faults trace back to sensor setup issues. Plant teams frequently skip step-by-step checks to meet tight project timelines. This checklist targets Bently Nevada machinery monitoring deployments specifically. It guides automation engineers through verification steps toward final project handover.
1. Pre-Commissioning Hardware and Site Validation
Cross-reference every delivered Bently Nevada module against approved BOM revisions. Inspect cabinet grounding carefully to keep electrical noise out of low-voltage sensor signals. Route sensor cables at least 30 cm away from high-power motor wiring. In addition, confirm that ambient cabinet temperature stays within the 0 to 55°C range. Review wiring schematics for DCS and PLC interlock interface terminals before power-up.
2. Proximity and Vibration Sensor Field Calibration
Mount each probe and measure target gap voltage at the shaft surface. Maintain the recommended gap between 0.8 mm and 1.2 mm for standard probes. Record raw voltage readings for every channel into site test logs. Furthermore, check cable integrity for broken shielding or loose connectors. One faulty proximity probe can disable the entire machinery protection logic.
3. Analog Channel Loop and Module Functional Testing
Power up Bently Nevada racks in sequence, one chassis at a time. Use a signal injector to feed known values into each monitoring channel. Compare local rack readings against values displayed on the DCS HMI. Acceptable signal deviation must stay below ±2% of the input reference. Therefore, engineers can confirm stable signal transfer across control systems.
4. Alarm Threshold Tuning and Trip Logic Verification
Set warning and shutdown limits following OEM rotating machine specifications. Simulate high vibration events to test relay outputs to PLC interlocks. Add 1 to 3 second time delays to filter harmless transient signal spikes. Save all parameter configurations to two separate backup storage locations. However, never modify trip thresholds without written client engineering approval.
5. Cross-System Communication and Data Integration Test
Verify Modbus or OPC communication between the Bently unit and plant DCS. Check 100% of data tags to ensure real-time refresh rates under 500 ms. Pull communication cables temporarily to confirm fault alarms trigger correctly. Industrial automation teams frequently overlook this integration validation step. Unreliable data links blind operators to early machinery damage signs.
6. Full System Dry Run and Formal Commissioning Sign-Off
Run a complete system simulation with maintenance and operations staff present. Resolve all open defects and classify remaining items for post-startup tracking. Collect signatures from automation, mechanical, and project stakeholders. Deliver calibration reports, parameter backups, and operation manuals to the site. As a result, the TSI system earns approval for live machine operation.

Field Application Case: 3500 Series TSI for Steam Turbine
A 12 MW power plant installed Bently Nevada 3500 TSI in 2025. The automation team used this checklist through all commissioning phases. They uncovered four misaligned probes and one noisy communication channel. Fixing these issues offline avoided a projected 14-hour turbine startup delay. The site reduced TSI-related startup risk by over 60% after full checklist use. In one loop test, a channel deviation of 3.1% was corrected to 0.8% before startup.
Author Insights: Lessons from 15 Years in the Field
Most TSI failures are not hardware defects but poor field installation practices. Always separate sensor calibration work from DCS and PLC integration tasks. Never skip offline simulation simply to hit aggressive project milestones. For industrial automation, traceable test records reduce future audit risk. Standard checklists create consistent quality across multiple plant sites.
Written by Gu Jinghong, industrial automation engineer specializing in PLC & DCS solutions for oil, gas and chemical industries.